Blended $285.44/MWh

Baseload

Demo
Data Center Energy · Derivation-Transparent
Analysis…
Start here · five cases, sixty seconds each
I.

The Portfolio

Blended all-in cost
per IT MWh, portfolio
IT capacity
1.60 GW
1.86 GW grid load
Annual energy
13.0 TWh
purchased per year
Annual spend
$3.20 B
all-in, per year
Construction capital
$16.76 B
excl. IT hardware
Emissions
5.01 Mt
CO₂ location-based / yr
United States map of portfolio sites and available marketsPacific Northwest200 MWERCOT NorthMISO South1.00 GWPJM West400 MWPJM DominionSoutheast regulatedMISO WestCarolinasDesert SouthwestCAISO Silicon ValleyNYISO UpstateNew England
Committed market — area ∝ MW · badge counts its projectsAvailable market
ProjectCapacityIT MWAll-in$ per IT MWhAnnual$ per yrCODmonth
Pacific Northwest
Non-RTO / BPA
PJM West
PJM
▸MISO South
MISO

Total committed: 1.60 GW IT · 1.86 GW at the meter. The capacity field is a lever — resize any commitment and the whole instrument re-prices.

The portfolio, over time

energizations · docketed ramp (50/65/80/90%) · spend vs load

The snapshot above, unrolled onto the calendar: construction capital draws flat across each project's wait to its COD month (the ledger's own draw), load arrives on the docketed hyperscale ramp stepping on contract anniversaries from that month — contracts step with it, so the demand charges do too — and the fixed charges run at full from energization, halls full or not. Portfolio reaches 1.86 GW at full ramp in 2035.

2026 — construction outlay: $5.38 B262027 — construction outlay: $5.38 B272028 — construction outlay: $3.35 B2028 — operating (ramped): $125 M2028 — capital charge + O&M: $671 M2028: MISO South · Jul 2028 energizes282029 — construction outlay: $1.33 B2029 — operating (ramped): $287 M2029 — capital charge + O&M: $1.34 B292030 — construction outlay: $1.33 B2030 — operating (ramped): $362 M2030 — capital charge + O&M: $1.34 B302031 — operating (ramped): $637 M2031 — capital charge + O&M: $2.28 B2031: Pacific Northwest · Jan 2031, PJM West · Jan 2031 energizes312032 — operating (ramped): $750 M2032 — capital charge + O&M: $2.28 B322033 — operating (ramped): $839 M2033 — capital charge + O&M: $2.28 B332034 — operating (ramped): $882 M2034 — capital charge + O&M: $2.28 B342035 — operating (ramped): $924 M2035 — capital charge + O&M: $2.28 B352036 — operating (ramped): $924 M2036 — capital charge + O&M: $2.28 B362026: 0 MW average at the meter2027: 0 MW average at the meter2028: 295 MW average at the meter2029: 679 MW average at the meter2030: 856 MW average at the meter2031: 1.34 GW average at the meter2032: 1.56 GW average at the meter2033: 1.72 GW average at the meter2034: 1.79 GW average at the meter2035: 1.86 GW average at the meter2036: 1.86 GW average at the meter$5.38 B1.86 GW
construction outlay operating, ramped capital charge + O&M load at the meter energization
YearLoad MWRampTWhOutlayOperatingFixedEnergizes
20260—0.0$5.38 B——
20270—0.0$5.38 B——
202829515.9%2.1$3.35 B$125 M$671 MMISO South · Jul 2028
202967936.5%4.8$1.33 B$287 M$1.34 B
203085646.0%6.0$1.33 B$362 M$1.34 B
20311,34372.2%9.4—$637 M$2.28 BPacific Northwest · Jan 2031, PJM West · Jan 2031
20321,56384.0%11.0—$750 M$2.28 B
20331,72492.7%12.1—$839 M$2.28 B
20341,79296.3%12.6—$882 M$2.28 B
20351,860100.0%13.0—$924 M$2.28 B
20361,860100.0%13.0—$924 M$2.28 B

Ramp: AEP Schedule DCT Load Ramp Contract Capacity steps (PUCO 24-508-EL-ATA) on contract anniversaries from each project's COD month — a calendar year prints the mean of its twelve monthly shares, ramped load over full-ramp load — and ramp contracts step the demand determinants with the load · outlay drawn flat by month across each project's wait (2026 commit) to its COD month, the ledger's own draw, so §VII's capital block foots to it · fixed charges (annualized capital + O&M) at full from energization · energizes = the COD month the ledger dates (rounded to the month where a slip lands off the grid) · directional.

The call · siting & hedging
Where the load belongs

Lead with MISO South — low all-in cost and quick to power. Weigh PJM West against the leaders — a high power price and a long road to energization — and hold it only for what the cost model doesn't price (fiber density, ecosystem, optionality).

What to do about price risk

Of the $838M open power position, $244M clears on ISO hubs (PJM Western Hub) — the curve-tradeable slice — while $593M is tariff-priced or bilateral, hedgeable contractually (PPA, or OTC indices like Mid-C) but not on a cleared curve (§IV bands the whole exposure). Locking ~50% of the hub slice narrows its ±20% hub-price swing from ±$49M to ±$24M for a $6M forward premium.

Site scorecardweighted: cost · speed · headroom · carbon · basis
1
MISO SouthLead1000 MW
$263/MWh · 2.5 yr to power · open grid
Strongest on low all-in cost and quick to power.
2
Pacific NorthwestHold200 MW
$295/MWh · 5.0 yr to power · tightening grid
Strongest on a clean grid.
3
PJM WestTrim400 MW
$338/MWh · 5.0 yr to power · tightening grid
Weakest on a high power price and a long road to energization.

Directional screen off the solved portfolio — reweight the sliders in §II and the call re-derives. Not a trade, not investment advice.

The full brief behind the call — printable — is §XII, The Memo.